Kerb and Channel Renewal Program and Pedestrian Ramp Upgrades 2024/25

  • Project typeRenewal Project
  • Project value$115,000
  • Project scheduleIn Progress
  • Completion Date10 March 2025

The 2024-2025 Kerb and Channel Renewal Program and Pedestrian Ramp Upgrades are now underway. Through this initiative, sections of kerb and channel and kerb ramps within the locality of Yea will undergo renewal, enhancing the quality and longevity of the stormwater and pedestrian infrastructure in the shire. Please note, these repairs will be on specific damaged sections, not replacing the whole street. See the table below for locations.

Below is a list of the roads scheduled for works, along with the planned week for each project (weather permitting).

If you would like to check whether these works will affect access to your property, please use the links provided next to each road name. For a broader view of the scheduled works and locations, please refer to the map below.

Location Status Expected commencement date (week commencing) Location 
Kerb and Channel Renewal Program 2024-2025
East St Works scheduled 28 January 2025 Kerb-1
Kerb-2
Kerb-3
Kerb-4
Kerb-5
Meara St Works scheduled 28 January 2025 Kerb-1
Kerb-2
Kerb-3
The Parade Works scheduled 28 January 2025 View location
Snodgrass St Works scheduled 28 January 2025 Kerb-1
Kerb-2
Kerb-3
Kerb-4
Raglan St Works scheduled 3 February 2025 Kerb-1
Kerb-2
Kerb-3
Miller St Works scheduled 24 February 2025 View location
Pechell St Works scheduled 3 March 2025 Kerb-1
Kerb-2
Pedestrian Ramp Upgrades 2024-2025
Webster St Works scheduled 28 January 2025 Ramp-1
Ramp-2
Nolan St Works scheduled 3 February 2025 Ramp-1
Ramp-2
Melbourne Rd Works scheduled 10 February 2025 View location
North St, Aldous Ave and Racecourse Rd Intersection Works scheduled 10 February 2025 Ramp-1
Ramp-2
Ramp-3
Ramp-4
Ramp-5
Ramp-6
North St and Francis St Intersection Works scheduled 10 February 2025 Ramp-1
Ramp-2
Pelissier St (Rail Trail Entrance) Works scheduled 10 February 2025 View location
High St Works scheduled 17 February 2025 Ramp-1
Ramp-2
Ramp-3
Ramp-4
Goulburn Valley Hwy Works scheduled 17 February 2025 Ramp-1
Ramp-2
Australia Post Office (Pelissier St) Works scheduled 17 February 2025 Ramp-1
Ramp-2
Mary St Works scheduled 24 February 2025 Ramp-1
Ramp-2
Anne St Works scheduled 24 February 2025 Ramp-1
Ramp-2
Ramp-3
Station St (North side) Works scheduled 24 February 2025 Ramp-1
Ramp-2
Ramp-3
Ramp-4
Ramp-5
Whatton Place and Loan St Intersection Works scheduled 3 March 2025 View location
Pechell St Works scheduled 3 March 2025 Ramp-1
Ramp-2
The Crescent Works scheduled  3 March 2025 Ramp-1
Ramp-2