Cathedral Close and Buxton Rise Sealing Upgrade 2024-2025

  • Project typeRenewal Project
  • Project value$200,000
  • Project scheduleIn Progress
  • Completion Date25 April 2025
Buxton Rise Sealing.png

The 2024-2025 Cathedral Close & Buxton Rise Sealing Upgrade is now underway. Through this initiative, the table drains will be reformed to improve drainage along the length of the road, the sealed sections of Buxton Rise & Cathedral Close will be resealed, and unsealed sections of these roads will be reshaped and sealed - enhancing the quality and longevity of the stormwater and road network infrastructure in the shire. In addition to this, a hardstand area will be formalised adjacent to the Buxton Memorial Hall to facilitate student drop-offs and parking for the Buxton Primary School.

The funding for these upgrade works is provided by the Australian Government under Round 4 of the Local Roads and Community Infrastructure (LRCI) grant program.

For a broader view of the scheduled works and locations, please refer to the map below.

Works Status Expected commencement date (week commencing)
Reforming of table drains Works scheduled 24 March 2025
Preparation and sealing of Cathedral Close and Buxton Rise Works scheduled 31 March 2025
Construction of hardstand adjacent to Buxton Memorial Hall Works scheduled 7 - 14 April 2025

(Easter School Holidays)